Wrong dates in a new ClickUp project? Check the List template.

Checked against ClickUp's help articles on 26 November 2026

If your agency creates each new client project from a List template and the dates come out wrong, start with these checks. If an automation creates the List, also see the automation section below: it has its own date settings.

Checklist

  • Dates saved on the template. Open the List template and look at each task's start and due date. A task saved with only a due date will still have no start date after it's applied.
  • Kept or remapped. When you apply the template, check whether you're keeping the saved dates or choosing Remap Dates. Kept dates are the original ones, however old they are.
  • Start or end date. Remapping uses either a new start date or a new end date. ClickUp suggests start when you know when the project begins, and end when you know the deadline. Check that your team uses the same one each time.
  • Weekends. Check whether Skip Weekends is on. ClickUp's own example moves a Sunday start date to the Monday. ClickUp also notes that the preview in the Use Template window may not show the weekend change, so check the dates on the new tasks, not the preview.
  • Durations. If your workspace uses task durations and dependencies, remapped dates are worked out from each task's duration, and skipping weekends can shorten it. That can move due dates in ways the template's calendar doesn't suggest.
  • Test once. Apply the template to a test List with a start date you choose, and compare the new dates with the ones you expected.

A fictional example

An agency keeps a List template for website projects. The tasks and dates are invented. The template's tasks were saved with these dates:

Template taskStart dateDue date
KickoffMon 7 DecMon 7 Dec
DraftWed 9 DecFri 11 Dec
Launch checkNoneTue 15 Dec

A new client project should start on Monday 14 December. Someone applies the template, chooses to remap the dates, and sets the new start date to 14 December.

If ClickUp keeps the same calendar-day spacing across the whole template, Kickoff lands on 14 December, Draft on 16 to 18 December, and Launch check is due on 22 December, one week later than in the template. Launch check still has no start date: remapping moves the dates a task already has and doesn't add a missing one. Check this result in a test List before relying on it.

If the new dates match the template's dates, check whether the original dates were kept and which date was selected for the remap. Matching dates alone don't tell you which setting was used. If the dates are shifted but not by the amount you expected, check which date was used for the remap and whether weekends were skipped.

If an automation creates the List

A Create list automation applies the template with its own date setting, chosen when the automation is set up. It doesn't use whatever someone last picked when applying the template by hand.

  • Do not remap dates keeps the dates saved in the template. A project created this way gets the template's original dates.
  • Remap dates overwrites either the start or the end date of the tasks.
  • The new dates can come from a date on the task that triggered the automation. In ClickUp's example, the request task is closed on 3 March, and that becomes the project's start date. If your project dates follow the wrong date, for example a proposal's due date instead of the agreed start, check which date the automation reads.
  • Skip weekends is a separate setting in the automation.

What to confirm in a test List

ClickUp's remapping article says a task keeps the same number of calendar days between its own start and due date, weekends included. Confirm the rest in your own workspace: the full result for your template, including the gaps between different tasks; which date the shift is measured from; which date fields an automation can read from the triggering task; and where the automation creates the new List.

Sources: Remap dates in templates · Create a List and apply a template using Automations · Task durations in templates. ClickUp may change its menus and options after the date above.

When dates are part of a bigger setup problem

If wrong dates keep turning up alongside other fixes after a new client project is set up, the NZ$290 pilot review looks at your whole setup process, from approval to ready, and gives you a written report. A short email is enough to start.

dre.businessteam@gmail.com

Open email draft

If the draft doesn’t open, start a new message in your usual email app or webmail. Use the address above and copy the template below.

Show email template to copy

Subject
Quote request: ClickUp project-setup review

Message
Hi Dre,

I'd like to discuss the scope of a ClickUp project-setup review. A few lines are fine.

Agency name:
How a new client project starts in ClickUp today:
Where client approval is recorded:
Roughly how many projects start each month:
If anything needed fixing after the last new client project was set up, what happened?

How did you find this page? (optional)

(No screenshots or client names yet. I understand you'll ask for screenshots only after a quote is accepted.)

What you send is handled as described in the privacy notice.

Back to the review

Agency Workflow Studio

ClickUp project-setup reviews

Pilot terms · Privacy

ClickUp, Microsoft Excel and Google Sheets are third-party products. No affiliation or endorsement is implied.